Location: Norton House
Client: University Housing
Schedule:
- Design: August 2023 - February 2025
- Construction: May 2025 - August 2025
- Beneficial Occupancy Date (BOD): 8.7.25
Financials:
- Budget: $5.3M
- Total project cost: $4.6M
Scope of Project: This project upgraded restroom and shower facilities to include contemporary finishes and fixtures while providing residents with increased privacy. The work also reduced the student to restroom fixture ratio from 9:1 to 7:1. Residential floor community space was renovated to include additional amenities like “Zoom Rooms” for virtual meetings, improved and more accessible kitchens, and reimaged study areas. The community area on the first floor was envisioned as a building-wide hub to include state-of-the-art study spaces, updated kitchens, and multipurpose common spaces for collaboration and living.