Sherman House Renovation

Location: Sherman House, North Residential Village

Client: University Housing

Schedule: 

  • Design: August 2025 - November 2025
  • Construction: May 2026 - August 2026 
  • Beneficial Occupancy Date (BOD): 8.4.2026

Financials:

  • Total Budget: $5.7M
  • Total project cost: $5.1M

Scope of Project: The project upgraded restroom and shower facilities to include contemporary finishes and fixtures while providing residents with increased privacy. Residential floor community spaces were renovated to include additional amenities like “Zoom Rooms” for virtual meetings, improved and more accessible kitchens, and reimaged study areas. The community area on the first floor includes a building-wide hub and state-of-the-art study spaces, updated kitchens, and multipurpose common spaces for collaboration and living.