Tyler House

Location: Tyler House, North Residential Village

Client: University Housing

Schedule: 

  • Design: February 2024 - August 2025
  • Construction: May 2026 - August 2026
  • Beneficial Occupancy Date (BOD): 8.4.26

Financials:

  • Budget: $5.6M
  • Final Cost: $4.9M

Scope of Project: The project upgraded restroom and shower facilities to include contemporary finishes and fixtures while providing residents with increased privacy. Residential floor community spaces were renovated to include additional amenities like “Zoom Rooms” for virtual meetings, improved and more accessible kitchens, and study areas. The community area on the first floor is a building-wide hub which includes state-of-the-art study spaces, updated kitchens, and multipurpose common spaces for collaboration and living.